Ladies Mile Update December 2026

VIEW PROJECT LADIES MILE TOWNHOUSE MASTERPLAN →

Overview

Clarke Group has prepared this update to share progress with the community, including early works at 429 Ladies Mile and traffic on SH6.

What is happening on site at 429 Ladies Mile?

As expected in our July update, machinery has moved on to 429 Ladies Mile to begin preparatory works for essential infrastructure, like electricity and wastewater pipes. These works will be carried out under resource consent rules, with erosion and sediment controls.

These essential civil and infrastructure works will start in early 2027 and should be completed around mid 2027 in preparation for building to start.

Some existing vegetation has been removed to enable these works. New planting, including street trees, parks and green connections, is a core part of the precinct’s design.

Will construction traffic add to congestion on SH6?

We want to keep construction traffic off SH6 at the busiest times. A traffic management plan for 429 Ladies Mile has been submitted, including heavy vehicle movements outside peak hours, site access and haul routes.

How many homes are planned for Ladies Mile, and how many will Clarke Group build?

The plan for the whole Te Pūtahi Ladies Mile precinct anticipates around 2,400 homes. The precinct has several landowners, and it will be built in stages over many years as sites are consented and infrastructure is delivered. Clarke Group has acquired more than 13 hectares across 429, 465 and 489 Ladies Mile.

At 429 Ladies Mile, a consent is in place for 287 homes and a revised application for up to 443 homes is with QLDC. No more than 287 homes can be occupied until key transport upgrades, including the traffic signals at Stalker Road intersection, are completed.

Will thousands of new homes mean thousands of extra cars on SH6?

Clarke Group understands that traffic congestion is a matter of concern and The Shotover River Bridge is a real ‘pinch point’ for local residents. The Ladies Mile developments are being designed with that constraint front of mind, not as an afterthought.

What matters for SH6 is how many trips are made at peak times, and how many of those cross the Shotover River Bridge. Work is well underway by NZTA, QLDC and independent experts to assess and understand what we all need to do to reduce traffic impacts.

Independent modelling by Mott MacDonald shows that how the Ladies Mile corridor is developed makes a huge difference to traffic outcomes. A purely residential development with no local services would generate the highest bridge demand. A ‘mixed-use’ community development that includes a new local school, new supermarket/retail, employment and alternative transport options can reduce bridge crossings significantly compared to a ‘residential-only’ base case.

What is happening with the roading and intersection upgrades?

Construction of the new intersection at Howards Drive has begun in partnership with NZTA. Further intersection works, including a new T-intersection at Tylden Road, are planned.

When can I see more of your plans?

Masterplans and designs are underway and will be shared on our website when finished. Our Ladies Mile display suite is being planned and we’ll provide a further update in the new year.

Where can I ask a question?

If you have a question about Ladies Mile that is not covered here or in our July update, please contact us here. We will post updates on our website.